Answer Key: Self-Test C-1.7.2
- Calculate the total fall to the nearest [latex]\frac{1}{8}[/latex] inch:
- [latex]11\frac{7}{8}\text{"}[/latex]
- Calculate the total fall to the nearest [latex]\frac{1}{8}[/latex] inch:
- [latex]15\text{"}[/latex]
- Calculate the pipe length:
- [latex]47\text{' }6\text{"}[/latex]
- Calculate the pipe length:
- [latex]88\text{'}[/latex]
- Calculate the grade in inches per foot:
- [latex]\frac{1}{8}\frac{\text{"}}{\text{ft.}}[/latex]
- Calculate the grade as a percentage:
- 0.95%
- Calculate the total fall to the nearest [latex]\frac{1}{8}[/latex] inch:
- [latex]16\frac{1}{4}\text{"}[/latex]
- Calculate the total fall to the nearest [latex]\frac{1}{8}[/latex] inch:
- [latex]26\frac{3}{4}\text{"}[/latex]
- Calculate the length:
- 16.2 m
- Calculate the length:
- [latex]199.5\text{'}[/latex]
- Calculate the grade in inches per foot:
- [latex]\frac{1}{16}\frac{\text{"}}{\text{ft.}}[/latex]
- Calculate the grade as a percentage:
- 0.54%
- Calculate the total fall to the nearest [latex]\frac{1}{8}[/latex] inch:
- [latex]4\frac{3}{4}\text{"}[/latex]
- Calculate the total fall to the nearest [latex]\frac{1}{8}[/latex] inch:
- [latex]22\frac{3}{4}\text{"}[/latex]
- Calculate the pipe length:
- [latex]100\text{'}[/latex]
- Calculate the pipe length:
- [latex]36\text{' }11\frac{3}{4}\text{"}[/latex]
- Calculate the grade in inches per foot:
- [latex]\frac{1}{8}\frac{\text{"}}{\text{ft.}}[/latex]
- Calculate the grade as a percentage:
- 1%
- Calculate the total fall to the nearest [latex]\frac{1}{8}[/latex] inch:
- [latex]10\frac{3}{8}\text{"}[/latex]
- Calculate the total fall to the nearest [latex]\frac{1}{8}[/latex] inch:
- [latex]58\frac{1}{2}\text{"}[/latex]
- Calculate the length:
- [latex]144.23\text{'}[/latex]
- Calculate the length:
- [latex]360\text{'}[/latex]
- Calculate the grade as a ratio:
- 1:50
- Calculate the grade as a ratio:
- 1:300
- Convert each measurement to engineer’s measurement (3 decimal places):
- [latex]18.5\text{'}[/latex]
- [latex]15.417\text{'}[/latex]
- [latex]32.75\text{'}[/latex]
- [latex]33.833\text{'}[/latex]
- [latex]35.938\text{'}[/latex]
- Convert each measurement to builder’s measure (nearest [latex]\frac{1}{8}\text{"}[/latex])”
- [latex]84\text{' }3\frac{1}{4}\text{"}[/latex]
- [latex]93\text{' }1\text{"}[/latex]
- [latex]106\text{' }8\frac{1}{2}\text{"}[/latex]
- [latex]123\text{' }5\frac{1}{4}\text{"}[/latex]
- [latex]156\text{' }11\text{"}[/latex]
- A house construction site has a benchmark of 100.00′, basement floor elevation of 94.20′, first floor elevation of 103.75′ and second floor elevation of 113.00′.
- How far below the benchmark is the basement floor?
- [latex]5.8\text{'}[/latex]
- How far above the benchmark is the first floor?
- [latex]3.75\text{'}[/latex]
- What is the distance from the basement floor to the first floor?
- [latex]9.55\text{'}[/latex]
- What is the distance from the first floor to the second floor?
- [latex]9.25\text{'}[/latex]
- How far below the benchmark is the basement floor?
- The low end of a sanitary building drain has an elevation of 91.55 feet. The grade is [latex]\frac{1}{4}[/latex] inch per foot.
- What is the elevation of a fitting 10′ upstream of the low point?
- [latex]91.65\text{'}[/latex]
- What is the elevation of a fitting 25′ upstream of the low point?
- [latex]91.81\text{'}[/latex]
- What is the elevation of a fitting 10′ upstream of the low point?
- Refer to Figure 27 to solve for the unknown values.
- [latex]86.000\text{'}[/latex]
- [latex]86.333\text{'}[/latex]
- [latex]87.646\text{'}[/latex]
- [latex]88.771\text{'}[/latex]
- [latex]92.646\text{'}[/latex]
- [latex]92.146\text{'}[/latex]